An effort by the City of Cambridge to improve Harvard Square’s streets
and sidewalks—estimated to cost over $3 million—has been delayed
because construction bids have exceeded the project budget and the
engineer’s estimates by more than one million dollars.
“The city did fund the $3.5 million that would have allowed
construction to begin this fall,” said John DiGiovanni, president of
the Harvard Square Business Association and member of the Harvard
Square Design Committee.
But the design committee who is spearheading the effort is now in the
process of rebidding the project. In a letter to the committee members
on December 9, 2005, Community Development Project Manager Katherine
Watkins said that bids are due in January and that construction is
anticipated to begin in the Spring of 2006.
“We’re certainly on track in terms that it’s moving forward, although
our original intention was to begin this fall,” said Watkins.
She cites the high cost of lighting and the difficult working
environment of the Square as reasons for the high construction bids in
the letter. Watkins said, however, that the committee has recently “set
up a contract so that an entire street segment could be eliminated from
the project [in order to] move forward and get as many improvements
done as possible within the budget.”
Thomas J. Lucey, Harvard’s director of community relations for
Cambridge, said that the project is going to take much longer than
initially expected and will “depend a little on the city’s capacity to
fund its capital program, of which this is a part.”
Although many streets and sidewalks in the Square need improvement,
Lucey said that he could not recall receiving complaints about the
sidewalks. But concerns are sometimes raised about crosswalks (such as
that across from Johnston gate) “when areas of pedestrian safety do
come into play,” he said.
The $3 million project is Phase One of a larger three-phase project
whose ultimate goal is “to make the public spaces as inviting and
accessible as possible,” DiGiovanni said. Church Street, Winthrop
Street, and Lampoon Plaza are among the areas scheduled to be
renovated. Although DiGiovanni predicts that a “manageable goal” is to
have Phase One begin and end in 2006, he could not predict when the
whole project would be completed.
While sidewalks, bus stops, and pedestrian safety are major concerns of
the committee, DiGiovanni said that much thought has been put into a
detailed plan to “transform Palmer Street into the most photographed
street in Harvard Square.”
Palmer Street, the cobblestone alley between either entrance of the
Coop, is scheduled to be completed as part of Phase One of the project
that will begin in the Spring.
The street will include special lighting and a screen that will drop
from the bridge between the two Coop buildings; essentially, the street
will become a pedestrian-friendly plaza. This art project was funded by
a group of private property owners including himself, DiGiovanni said.
“The community has been terrific in the process,” said DiGiovanni. “We
would all like this to go faster, but it takes longer than you think.”
Read more in News
For Harvard, No Accounting 101