The new dining hall at South House, beset by numerous delays since construction began in late August, will be ready for occupancy in mid-June, five months after its scheduled completion date, Robert Thomas, manager of the Construction Management Division of the Harvard Planning Office, said Monday.
The resignation of the project manager of the construction company, problems with the acquisition of materials and bad weather, all contributed to the delay.
"You have here a negative dynamic motion where its problems tend to feed on themselves and they have a snowball effect," Thomas said.
The problems began in the fall with a three-week delay in the steel delivery, and the wet weather which prevented completion of the concrete foundation. Thomas said.
John B. Cruz, the owner of the construction firm, said yesterday the winter storm knocked down the staging for the brick work two times and together with the heavy snow helped to delay the project four weeks.
Read more in News
Tuckerman Ties for Scoring Crown With Rockett in Ivy League SoccerRecommended Articles
-
Weld to Be Ready by Dec. 31Construction workers removed much of the scaffolding from Weld Hall's exterior yesterday, giving University officials reason to anticipate completion of
-
Behind the South House Dining HallSouth House had more than its share of troubles since the River Houses started going co-ed in 1972. What was
-
Transfer Applications To Quincy Due SoonApplications for transfer to Quincy House are due in University Hall on or before Monday, Dec. 1, John M. Bullitt
-
House Debates SycamoresThe legislative bill (H3554) that would delay the construction of the Memorial Drive underpasses will probably come before the Massachusetts
-
Work on Yale Bowl DelayedLack of available funds threatens to seriously delay the completion of the Yale Bowl, which was expected to be finished
-
New Squash Courts at Harvard ClubThe Harvard Club of Boston has announced, the completion of five new squash courts which brings the total of courts