Construction work on the Med Area power plant, already delayed by more than a year when Harvard had to hire a new engineering firm to improve the design developed by its original firm, will not proceed beyond the foundation for at least another month.
The board of the Boston Redevelopment Authority (BRA) this week asked its attorney to draw up a statement granting the project necessary approval, but the Department of Environmental Quality Engineering (DEQE) must also approve the project.
Final approval from the environmental quality department will not come for at least 30 days, a DEQE official said this week.
And the BRA's approval, according to the board chairman's recommendation, will be granted on condition that the Medical School and affiliated hospitals agree to draw power from the plant.
Read more in News
Developer Transports 'Priceless' Tree 20 FeetRecommended Articles
-
MATEP Clean Air Exemption UpheldThe Second Circuit U.S. Court of Appeals recently upheld the Environmental Protection Agency's (EPA) exemption of Harvard's Medical Area Total
-
Power Plant May Receive New HearingHarvard yesterday filed a petition seeking to overturn a state environmental agency's disapproval of the electric generators planned for the
-
The Power Plant: Struggles ContinueThe battle lines are drawn and the strategies set as Harvard moves ahead with the building of the Medical Area
-
Turn It OnO NCE UPON A TIME, Harvard had a brilliant idea. Forecasting increases in energy prices and decreases in supply, the
-
One More HeadacheSome headaches just won't go away. Harvard faces yet another lawsuit in connection with its $110-million Medical Area power plant
-
Court Hears Power Plant ArgumentsAfter listening to an hour of arguments in Suffolk Superior Court yesterday from Harvard lawyers and from opponents of the