The U.S. Government and the John F. Kennedy Library Corporation will today take title to the MBTA's Bennett Street train yards--the future site of the Kennedy Library.
The MBTA will receive $1,330,112 from the Library Corporation and $6,097,854 from the Commonwealth of Massachusetts. The Great and General Court (state legislature) appropriated its contribution in 1965 as the Commonwealth's official memorial to the late President Kennedy.
Under the terms of the deed the MBTA will continue to use the Bennett yards rent-free until Jan. 1, 1970, when construction on the Library is scheduled to begin.
A long delay in finding another site for the Bennett transit facility could post-pone ground-breaking beyond that date. If this happens, a Library spokesman said last night, the MBTA will probably be given an extension on the use of Bennett.
The latest proposed site for the replacement facility--Mattapan Square--is presently being considered by the MBTA's five-man Board of Directors.
The plan for the new site--announced February 1 by MBTA General Manager Leo J. Cusick--will cost $12-million. Politicians in the area have raised strong objections to the plan.
Read more in News
TomorrowRecommended Articles
-
State Solicits Bids For MBTA YardMore than 14 months after the Kennedy Library Corporation decided not to build its JFK memorial library on the MBTA
-
1000 Residents Protest Mattapan MBTA SiteOne thousand Mattapan residents attended a public meeting Tuesday to protest MBTA extension plans which would place a rail yard
-
City Checked On Plan For JFK LibraryCity officials have apparently failed to obtain the Bennett St. MTA Yards as a site for the Kennedy Library. Their
-
Harvard Center Joins LibraryPlans are underway for a $10 million Harvard research and teaching center in public and international affairs as part of
-
Volpe Suggests New MBTA Site To Break JFK Library DeadlockGov. John A. Volpe has acted to break the deadlock over the relocation of the Bennett St. MBTA yards which
-
MBTA, Pennsy Agreement Ends JFK Library DelayAfter more than four years of delay, the way has finally been cleared for construction of the John F. Kennedy